UHPC lined hydraulic conveyor pipelines for brine in salt mines

More than 14 years ago, a high-pressure-safe
(loadable up to max. 100 bar / 1450 psi) brine
hydraulic transport pipeline with UHPC wear
protection was installed as a test for other lines.

The pipe installation took place underground. In
addition to the extreme pressure, the line
should be highly wear-resistant and highly
corrosion-resistant.

After all these years, we had the opportunity
to check this line together with the customer
on site.

A pipe element was also removed from the
line and cut open to inspect the UHPC lining.
Neither the customer nor we expected such an
extremely good result after all these years of
operation.

The UHPC lining has only lost a few
millimeters from its 30 mm lining.
Thanks to the seamless, waterproof UHPC
lining, no expensive corrosion protection was
necessary during wear protection assembly.
Which made assembly much faster and less
expensive than the linings previously used.
 



WPE DK International

Phone: 0049 176 601 73146
E-mail: info@wpe-dk.dk
Homepage: www.wpe-dk.com
















Past and future of concrete in security and military

In the past there have always been interesting
safety solutions with concrete.
Some were successful, some were not. A
success story were bunker structures
underground or above ground for the navy, air
force and army. Even today, concepts for
military and civil security rooms are carried
out with concrete structures.
The next generation in which concrete is
replaced by Ultra High Performance
concrete, or UHPC for short, has been used
very successfully worldwide for a few years.
These UHPC security concepts resist the
strongest attacks, penetration is almost
impossible with the current known weapons.
UHPC security concepts are also increasingly
used in the civil construction industry for
security constructions in safes and security
rooms, coastal protection, fire protection, storm
protection, disaster protection and terrorism
protection.
We are constantly developing UHPC for new
applications, such as floating, unsinkable
platforms that can be used anywhere in the
world, both civil and military.
 
 
WPE DK International

Phone: 0049 176 601 73146
E-mail: info@wpe-dk.dk
Homepage: www.wpe-dk.com




UHPC Phalt a semi rigid top layer for all areas of an airport

Our nanotechnology for UHPC binder is now
over 30 years old and has been used in a wide
variety of areas worldwide.

From the beginning, the idea was to create a
material combination that combines the best
material properties of both products in an ideal
and flexible manner.
We call this combination material UHPC-Phalt.

The technique is simply, lay a coarse-grained,
porous, locally produced standard asphalt and fill
the pores with an extremely liquid UHPC concrete.

The result is that a flexible, temperature-resistant, 
high-pressure-resistant and extremely resilient, 
frost and de-icing salt-resistant, long-lasting
runway surface is created.

Benefit:
High axle loads, extreme ambient temperatures,
limited construction time and
constrained budgeting.

Standard laying machines and mixing machines
can be used for processing. Asphalt assembly
companies can easily lay this combination of
such materials

Local asphalt qualities can easily be used for
processing.
Fine sand or desert sand can be used for the
UHPC concrete.

Our UHPC binder can be flexibly adapted to
customer requirements. Curing speeds can be
adapted to customer requirements so that the
laying speeds of the laying machines can be
used to the maximum.



WPE DK International

Phone: 0049 176 601 73146
E-mail: info@wpe-dk.dk
Homepage: www.wpe-dk.com



Pipeline repair in a potash mine

When I visited a potash mine, I noticed this "cemetery"
of used pipe parts for the hydraulic potash extraction.
There are around 200 pipe parts of different diameters,
lengths, angles and radius. All parts that were specially
manufactured for this production. The pipe parts are all
lined with cast basalt and have a 3-component
anti-corrosion coating. On average, these new pipe parts
cost EUR 700.00 / piece. So there is a value of at least
EUR 140,000.00. Since the pipe parts show more or less
wear damage, all should be disposed of. The disposal
costs amount to at least EUR 12,000.00. The new price
for the pipe is approx. 156,000.00 EUR and the delivery
time is at least 3-4 months.

I explained to the plant management that we can repair
all the pipe parts. We would remove the existing and
partially worn cast basalt lining and replace it with a
new UHPC wear protection lining. I calculated the
budget costs for this at EUR 66,000.00. The repair work
takes approximately 2 months. Here, however, we could
orient ourselves according to the wishes regarding the
installation sequence to the customer and always repair
the pipe parts that he needs at short notice.

Our customer decided on a new lining instead of a new
production and saved 90,000.00 EUR and at least 1-2
months delivery time.

Today there are no more "cemeteries" for used pipeline
parts in his plants.





www.hhbc-consulting.de