We have an order to supply and install a UHPC wear protection liner in a new grinding system at an ore processing plant in Bahrain. The new grinding system was designed
and delivered by a large German plant manufacturer.
UHPC wear protection
was specified by this plant manufacturer as wear protection for his
system.
The contract included the lining of pipelines, cyclones and separator systems. The assembly of a 25 mm / 1 inch UHPC wear protection liner with a total area of over 600 sq / 6450 sq ft was performed by a local installation company under the supervision of one of our supervisors.
24 hours after the individual plant elements were lined, they could be mounted in the ore processing plant.